Timeline

Week 1
  • 8/10 - Visit The Falls of Landen neighborhood for the first time and tour the Calvert model.
Week 2
  • 8/18 - Show husband and find out more about neighborhood, builder and floorplans.
Week 3
  • 8/24 AM - Preview flooring options
  • 8/24 PM - Price out options with Ryan
  • 8/27 - Meet with realtor to sell current home
  • 8/29 - Asked a bunch of questions, looked at lots, signed purchase agreement, $5,000 deposit
Week 4
  • 8/30-9/6 - Went on vacation to Walt Disney World
  • 8/31-9/2 - Decided on final lot location
Week 5
  • 9/9 - Official flooring appointment
  • 9/11 - First meeting with NVR and paperwork submitted
  • 9/11 - Guardian appointment
Week 6
  • 9/16 - Finalize flooring selections
  • 9/16 - Finalize Guardian selections
  • 9/18 - Finalize all selections with Ryan
Week 7
  • 9/21 - More paperwork to NVR
  • 9/25 - 2nd unit in building sold
Week 8
  • 10/1 - More paperwork to NVR, submitted to underwriting
Week 9
  • 10/7 - Next to build, construction timeline pending other purchaser's mortgage approval (1-2 weeks)
Week 10
  • 10/13 Approval to remove Wireless Access Point from Guardian
Week 11
  • 10/23 - Blueprints and permits ordered. Pre-construction meeting will be in November and could possibly be scheduled next week
Week 12
  • 10/26 - Turned in remaining 5% deposit. Toured recently completed Calvert's to see options and flipped floorplan. Lot staked and utility meters on lots.
  • 10/28 - Pre-construction meeting scheduled for 11/4. Digging to begin 11/10 (ish)
Week 13
  • 11/4 - Pre-construction meeting
Week 14
  • 11/10 - Dig Date!
  • 11/13 - Footers Poured
Week 15
  • 11/19 - Foundation Poured
  • 11/20 - Mortgage Approval from NVR
Week 16
  • 11/24 - NVR Acceptance Letter Signed. Forms removed. Dirt pushed back. Basement and garage floors being poured.
  • 11/27 - Basement and Garage floors complete. Supports constructed for covered porch. First load of lumber delivered (looks like walls and floors for all units).
Week 17
  • 12/3 - Framing has started. Floor almost complete, walls next.
Week 18
  • 12/6 - Walls started
  • 12/10 - Most walls roughly framed. First time walking in the house!
Week 19
  • 12/17 - Doors and windows have been delivered. Framing is mostly done, shingles are stacked on the roof. First time going upstairs.
Week 20
  • 12/21 - Party wall installation. Framing for covered porch.
Week 21
  • 12/30 - Mechanicals almost done. Windows in and doors being installed. Framing nearly complete.
Week 22
  • 1/5 - Pre-drywall Meeting. Insulation
  • 1/8 - Drywall started and locked interest rate with NVR
Week 23
  • 1/14 - Drywall continues, Cabinets and Doors delivered. 
Week 24
  • 1/21 - Finishing Drywall. First coat of paint. Ceramic floor and walls going in. Wood floor done. Cabinets, doors and trim being installed.
Week 25
  • 1/28 - Painting trim and walls. Lights installed and working. Siding done, starting the stone. Working on finishing the deck. Cabinets, vanity tops, and bathroom plumbing installed. Heat running.
Week 26
  • 1/31-2/6 - Cleaning. Final Electrical and Plumbing. Carpet.
Week 27
  • 2/7-2/11 - Inspection and Touch-Ups
  • 2/12 - Pre-Settlement
  • 2/12 - Closing!